I met with the contractor this afternoon on Yaronia Drive. We will most likely be delayed until early spring due to Columbia Gas running behind schedule on their relocations for Yaronia Dr and Glenmont Ave. The benefit to this may be an opportunity to make some adjustments to our storm sewer location and save some trees – but no promises yet.
Mark Timbrook, P.E.City of ColumbusSewer Systems Engineering SectionDivision of Sewerage and Drainage