Adena Brook Team Member Kip Patterson writes:

I attended the pre-work meeting this morning.

The work is scheduled to start on August 11th, but may not because of our good friends Columbia Gas not getting their preliminary work done.  The contractor folks are very nice and asked for our help perhaps with notifications.

They will have a lot of fill dirt to get rid of, if you know of any takers.  Realize that we are talking the smallest quantity being a large dump truck load.  They also need a site where they can store materials.

I also met Brian Haemmerle, an engineer with the water department.  He has just received the assignment to design the water line replacement for Lenappe and Canyon.  He is also going to look into the continuing leak under Cooke that is feeding Adena Brook.